CONSTRUCTION OF SUBHADRA BHAVAN

Construction Updates (Aug ’17 – Oct 7, 2017)

  • September 14, 2017: The making of steel reinforcements for all the columns was finished.
  • August 22, 2017: The making of starters for all the columns were finished.
  • August 17, 2017: Work resumed after the first floor slab was allowed to cure properly for one month.

Construction Updates (May ’17 – Jul ’17)

  • July 12, 2017: The concrete casting of First Floor Slab and Tie-Beams were completed.
  • July 1, 2017: The making of steel reinforcements for First Floor Slab and Tie-Beams was completed.
  • June 9, 2017: The construction of timber formwork for First Floor Slab was completed.
  • May 17, 2017: Concrete casting of the Elevator wall and Staircase were completed.
  • May 2, 2017: Concrete casting of all the First Floor columns were completed.

Construction Updates – Apr ’17

  • April 30, 2017: Construction of 26 out of 29 columns were completed.
  • April 14, 2017: The casting of Ground Floor slab along with tie-beams was done.
  • April 12, 2017: The making steel reinforcements for Ground Floor slab was completed.
  • April 7, 2017: The making of steel reinforcements for Ground Floor tie-beams was completed.

Construction Updates (Jan ’17 – Mar ’17)

  • March 20, 2017: The building of formwork for ground floor slab was completed.
  • February 28, 2017: The steel rod bindings, shuttering and casting for all the columns were completed.
  • February 24, 2017: The casting of ground floor staircase was completed.
  • January 21, 2017: The concrete casting of tie-beams at plinth and covers of tanks were completed.

Construction Updates (Sept ’16 – Dec ’16)

  • December 29, 2016: The making of steel reinforcements for RCC covers of tanks and for tie-beams at Plinth level were completed.
  • December 8, 2016: The inside of the Plinth was completely filled with fine quality white (silver) sand.
  • November 26, 2016: The casting of RCC walls for elevator at Plinth was completed.
  • November 3, 2016: The brickwork at periphery of Plinth and plastering at inner walls of the tanks were completed.
  • September 10, 2016: Underground Reservoir and Septic Tank was constructed.


MORE PICTURES OF PILE CAPS & PLINTH


Construction Updates (June ’16 – Aug ’16)

  • August 28, 2016: Concrete casting of all columns till Plinth level was completed.
  • August 6, 2016: Casting of RCC tie-beams above the Pile-Caps was completed.
  • July 20 – July 25, 2016: The spaces between the Pile-Caps were filled with silver sand.
  • July 19, 2016: The road in front of building site was repaired.
  • July 15, 2016: Concrete Casting of 25 Pile Caps was completed.
  • May 15, 2016: Construction of Deep Pile Foundation was finished.


MORE PICTURES OF PILE CAPS & PLINTH


Deep Pile Foundation –
The Process (Apr ’16 – May ’16)

** The images have been taken over a period of 1 month for a total of 96 Piles. To see the daily updates of Piling Click Here


MORE PICTURES OF DEEP PILE FOUNDATION