Construction Updates – IX (May, 2024)

Construction Updates – VIII (December 30, 2023)

Completion of 4th Floor Roof Slab

Construction Updates – VII

Construction Updates – VI

  • Work resumed after the first floor slab was allowed to cure properly for one month.
  • The making of starters for all the columns were finished.
  • The making of steel reinforcements for all the columns was finished.

Construction Updates – V

  • Concrete casting of all the First Floor columns were completed.
  • Concrete casting of the Elevator wall and Staircase were completed.
  • The construction of timber formwork for First Floor Slab was completed
  • The making of steel reinforcements for First Floor Slab and Tie-Beams was completed.
  • The concrete casting of First Floor Slab and Tie-Beams were completed.

Construction Updates – IV

  • The making of steel reinforcements for Ground Floor tie-beams was completed.
  • The making steel reinforcements for Ground Floor slab was completed.
  • The casting of Ground Floor slab along with tie-beams was done.
  • Construction of 26 out of 29 columns were completed.

Construction Updates – III

  • The concrete casting of tie-beams at plinth and covers of tanks were completed.
  • The casting of ground floor staircase was completed.
  • The steel rod bindings, shuttering and casting for all the columns were completed.
  • The building of formwork for ground floor slab was completed.

Construction Updates – II

  • Underground Reservoir and Septic Tank was constructed.
  • The brickwork at periphery of Plinth and plastering at inner walls of the tanks were completed.
  • The casting of RCC walls for elevator at Plinth was completed.
  • The inside of the Plinth was completely filled with fine quality white (silver) sand.
  • The making of steel reinforcements for RCC covers of tanks and for tie-beams at Plinth level were completed.


MORE PICTURES OF PILE CAPS & PLINTH


Construction Updates – I

  • Construction of Deep Pile Foundation was finished.
  • Concrete Casting of 25 Pile Caps was completed.
  • The road in front of building site was repaired.
  • The spaces between the Pile-Caps were filled with silver sand.
  • Casting of RCC tie-beams above the Pile-Caps was completed.
  • Concrete casting of all columns till Plinth level was completed.


MORE PICTURES OF PILE CAPS & PLINTH


Deep Pile Foundation –
The Process

** The images have been taken over a period of 1 month for a total of 96 Piles. To see the daily updates of Piling Click Here


MORE PICTURES OF DEEP PILE FOUNDATION